Linda L. Stoll
Superintendent, Wind Cave National Park
I have followed over the past months the dialogue about the proposed wastewater
transmission line project from Wind Cave NP to the City of Hot Springs. There
has been a great deal of editorial misinformation printed in the Star and
Journal, and some clarifications need to be made. The citizens of Custer
and Fall River Counties deserve to hear the facts. What follows is lengthy,
but if you want some FACTS here they are.
BACKGROUND:
FACT: Wind Cave National Park’s wastewater
treatment facility is undersized and poorly located to accommodate
the wastewater generated by park facilities and rainfall inputs.
The lagoons’ present location is shielded from the sun
and wind, so they do not evaporate adequately. Two lagoons were
built in 1964 but rarely held more than a couple of feet of effluent.
This lack of volume lead park officials to believe the lagoons
were leaking untreated sewage into the aquifer and undiscovered
cave below, so they were lined with impermeable liners in 1989.
They immediately began filling, proving they had been leaking.
To prevent them from overflowing in 1993, an emergency irrigation
permit was issued by the state. A third lagoon was added in 1996
to increase storage, but due to site constraints, it was not
large enough. Since then, the lagoons would have overflowed two
more times if not for additional emergency irrigation permits
in 1996 and 1999. When the last permit was issued, the park was
told in a letter from the South Dakota Department of Environment
and Natural Resources (SD DENR), dated July 13, 2000, that future
requests for irrigation of wastewater in this area will likely
not be granted. With the State no longer allowing emergency irrigation,
the park began seeking funding for a permanent solution.
FACT: Properly designed lagoons should rarely
fill to the brim. The lagoons are presently operating at near their
design capacity considering the SD DENR criteria requires three
feet of freeboard to prevent discharges due to extreme precipitation
years and dike and liner damage due to high winds and water levels.
The reason that the ponds have not overfilled since the spring
of 1999 is because land application in 1999 and 2000 drew the ponds
down to minimum levels. Over the past three relatively dry years,
the ponds have gained back over a million gallons. If nothing is
done, the ponds will again fill to the top at which point they
will overflow simply from daily use.
FACT: Some have suggested we should obtain a
permanent discharge permit to reduce the cost of this project.
Permanent permits do not exist. Discharge permits must be renewed
every five years. Such a permit would not come without substantial
cost due to the alterations that would be required by SD DENR.
We chose not to request such a permit, since surface discharge
of wastewater has a potential to negatively impact cave resources
which are believed to exist under the current lagoons and the area
used for irrigation. In addition, an unnatural water and nutrient
source would result in undesirable changes in plant and animal
ecology in the area of discharge, creating an unnatural environment
in a natural setting.
In the past, the SD DENR Ground Water Quality program raised concerns
over the suitability of our site for the irrigation of wastewater.
They have seen cases in the Southern Black Hills where water moves
very quickly through soil formations making the site unsuitable.
If the SD DENR were to grant a permit, there is no guarantee that
every five years the permit would be renewed. If the permit is
denied, we would be back where we started but without the current
funding to solve the problem. The bottom line is that surface irrigation
from the existing lagoons does not meet the purpose and needs identified
for the project even though it may be less expensive.
THE PROCESS:
FACT: While developing potential alternatives,
we discussed the project with City officials to determine if
connecting to the municipal system was a viable alternative.
As a result, the Common Council of the City of Hot Springs passed
Resolution 2002-10 on February 19, 2002, stating that the City
would receive the sanitary pipeline installed between the City
and Wind Cave National Park if that was the alternative selected
by the park. This resolution was published in the Hot Springs
Star on February 26, 2002. Had the City not made this commitment
to provide wastewater treatment service, the alternative would
have been dismissed from further consideration at that time.
FACT:
The Park sought public comments early in the development of possible
alternatives with a front page article
in the Hot Springs Star on March 5, 2002. The article explained
the problem, possible solutions, and asked for public input regarding
the alternatives being considered, issues or concerns related to
each of the proposed alternatives, and any new alternatives that
should be considered for wastewater treatment. We received no comments.
We strive to work together with our stakeholders to meet the project’s
objectives; yet we received no comments during the critical formation
period which set the project’s direction and alternatives.
FACT:
Prior to issuing the Draft Environmental Assessment (EA), an
interdisciplinary team comprised of representatives
from Rothberg, Tamburini & Winsor, Inc., Parsons Corporation,
the National Park Service (NPS) Denver Service Center, and park
staff analyzed 10 different alternatives during a Choosing by Advantages/Value
Analysis session, April 16-17, 2002. The alternatives analyzed
in the EA are those that met the project objectives to a large
degree, although not necessarily completely. The primary objectives
of the project are a) to protect public health, safety and welfare
by compliance with state and federal regulations in regard to wastewater
handling and treatment, b) to protect natural resources in the
park by eliminating surface discharge of wastewater, c) to provide
for visitor enjoyment by removing the highly visible and unsightly
wastewater treatment lagoons from their current site immediately
adjacent to the park’s main access highway, and d) to provide
a cost effective, environmentally responsible long-term solution
for the park’s wastewater treatment needs.
The Value Analysis (VA) study evaluated how well each of the 10
alternatives met the objectives of the project with consideration
given to initial capital costs and long term operational costs.
The process identified the pipeline to the City of Hot Springs
as being the alternative with the best benefit to cost ratio, i.e.,
over the long run, this alternative best met the project objectives
for the least cost.
The top three alternatives identified from the VA process were
then evaluated as part of the EA: building a sewer line into town;
building our own treatment plant; or relocating and building new
lagoons.
FACT:
The EA was available for public review and comment from April
4 to May 15, 2003. A public open house was
held on April 24, 2003, at the park’s visitor center. Comment
periods provide the public another opportunity to review and comment
on proposed actions having the potential to significantly effect
the environment, but they are not votes. The park received eight
letters and three identical petitions with 47 signatures during
the comment period.
Out of all the responses, there were two letters with substantive
comments that added substantive issues or facts to the debate.
In this case, as a result of one of the comments, an enhanced leak
detection system was added to the plan. Eventually, a point is
reached in project development when a decision has to be made and
work begun to fix the problem. In this case, the decision document,
the Finding of No Significant Impact (FONSI), was signed by the
NPS Regional Director on November 13, 2003.
On December 3, 2003, a contracting officer for the NPS signed
a contract with the City of Hot Springs and gave notice to proceed
with the plant certification and the design. Once construction
drawings are completed and approved by the State, construction
of a sewer line from the park boundary to the City limits can proceed.
PROJECT RESPONSIBILITIES:
FACT: The NPS relies on the technical expertise of contractors in
preparation of many of our documents, including engineering design and/or compliance.
In this process, NPS staff are contributors, reviewers, and approvers but generally
not authors. For this project, the NPS contracted with Parsons Corporation
(www.parsons.com) to evaluate the environmental impacts of the various alternatives
to ensure compliance with the National Environmental Policy Act (NEPA) and
to produce the EA. Parsons is a leading science and engineering consulting
firm. They did not do the engineering work associated with this project but
instead consulted with another NPS contractor working on the project as stated
on page 103 of the EA. Parson’s role was to evaluate the environmental
impacts of the various alternatives presented in the EA to ensure compliance
with NEPA. We have said all along we hired one of the top firms in the country
to produce the EA. However, some misinterpreted that Parsons also did the engineering.
The NPS and Parsons Corporation stand behind the document.
FACT: The VA and preliminary engineering design in the EA
was done by Rothberg, Tamburini & Winsor, Inc. (RTW) of Colorado (www.rtweng.com).
They specialize in providing professional consulting and engineering services
for the water and wastewater industry. RTW is an award-winning firm that
has received recognition at both the local and national levels.
COST:
FACT: The project was funded at $3.9 million, part of which is available for
construction. To date, we have spent well over $400,000, not counting salaries
of NPS staff working on this project, in development of the preferred alternative
in good faith based upon the resolution passed by the City Council and the
contract that was signed between the NPS and the City. To change directions
now would result in a substantial loss of a financial investment when some
are saying their concern is the expense of the project. At this point in time,
the cost of implementing another alternative, which will happen should the
contract with the city fail, would be considerably greater than completing
the sewer line into town.
PUBLIC SAFETY:
FACT: This project will add about 2.5 million gallons of wastewater
per year into the city system. On an annual basis, this is equivalent to the
amount of wastewater generated by about 70 people, or 30 single family homes.
The city plant has a design capacity of 1.54 million gallons per day. On the
peak day in 2002, the city plant treated 795,000 gallons of wastewater which
is about 52% of total capacity. The peak flow from the park will be about 25,000
gallons per day, less than 2% of the design capacity of the plant.
Another concern expressed
in the frequent editorials is about pollution of the Hot Springs
potable water well if this project
is completed. They wrote that the EPA estimates that 100,000 gallons
of Wind Cave sewage will leak into the Hot Springs groundwater
per year from leaking city sewer lines. The fact is, the EPA has
never inspected, tested, or evaluated the Hot Springs sewer lines
to determine how much sewage, if any, leaks from the lines. The
estimate published in the editorials is solely the opinion of that
author. Apparently this estimate is based on a statement in an
appendix of an Environmental Protection Agency (EPA) Report to
Congress from 1977 which he says reads: “Based on available
information, sewer leakage on the average is probably around 5%
of the total, with wide variations from system to system.” This
statement was vague even when it was written 27 years ago, and
today is very misleading when used in this manner.
If someone were going
to make a responsible estimate of how much wastewater is leaking
from the city sewer system, the first thing
should be to determine the condition of the system, probably by
talking to the people that operate and maintain the system. If
his estimate is accurate, in 2002 while the city plant treated
about 200 million gallons, 10 million gallons leaked into the ground
water. If there is a valid concern about the amount of Wind Cave
sewage leaking, the concern should be at least 100 times greater
for the existing conditions. If the amount of wastewater generated
by 30 new homes puts the city’s water supply in jeopardy,
should all development in Hot Springs be stopped now? The facts
do not seem to support the writer’s claims since the Hot
Springs wastewater treatment plant is in complete compliance with
the permit issued by DENR and is also well run as evidenced by
its winning an Excellent Operation and Maintenance Award from DENR
in 2001. For the project at hand, it is the responsibility of the
SD DENR, through the process of engineering design review, to ensure
the project proceeds in an environmentally safe manner. In a letter
written by SD DENR Secretary Steven M. Pirner, he states “DENR
is of the opinion that the preferred alternative can be designed
and constructed to meet state environmental standards.”
BENEFITS:
FACT: This project will provide the City of Hot Springs additional
revenue in sewer user fees while only taking up 2% of the City’s underutilized
plant which users are paying to operate and maintain anyway. If Wind Cave National
Park constructs its own treatment plant, taxpayers will pay to operate and
maintain two treatment plants within 15 miles of each other, when the existing
municipal plant would suffice. This project will allow property owners along
the Highway 385 corridor the opportunity to hook into the system, protecting
our water source from potential contamination from septic systems, while encouraging
growth that will add to the County tax base. We firmly believe that the sewer
line is the best for the NPS, for Custer and Fall River Counties, the City
of Hot Springs, and South Dakota, as well as being the best long-term investment.
This alternative also takes the best care of the park and your world-class
cave. |