In
late June, the Chattahoochee River NRA began a year long river access
construction project to improve the boat ramps.
The
nature of this project has a high level of complexity, due to
fluctuation with weather and the river flow and velocity. Therefore,
the schedule
may change during the course of construction. The projected schedule
below represents the park staff’s best efforts to anticipate the
course and sequence of this project. This listing will be
continuously updated as necessary and with as much advance notice as
possible.
Current as of August 15, 2006
Location
Construction Dates
Palisades
Sandy Point Step Down Ramp
Construction Completed*
Whitewater
Creek Step Down Ramp
Construction Completed*
Settles
Bridge Step Down Ramp
mid-January to late February
Jones Bridge
Boat Ramp mid-August
to late September
Johnson Ferry
Boat Ramp
late September to late October
Abbotts
Bridge Boat Ramp
late October to late November
Paces Mill Boat Ramp
late November to mid-January
*While the ramp has been constructed landscaping and other activities
are not completed. Planting will begin when weather is more conducive
to plant survival.
Throughout the time of construction, access points will be closed to
all public use and alternative points will need to be utilized for
river access or egress. During construction of the Paces Mill
location, alternative access will be established for public use in the
same general location.
“Everything is being done to keep river access disruptions to a
minimum,” said Cheri. “I encourage our park visitors to contact me if
they have any questions or concerns.”
For more
information, call 678-538-1210 or email CHAT_Superintendent@nps.gov.
|